Telus Conduit Installation - Phase I

Please be advised that Telus will be installing conduits in the corridors on all the residential floors, during the period of:

Friday, Dec 7/ 2018- Friday, Dec 21/2018

Work will be completed during the hours of 8:30 am- 4:00pm. Drilling/ hammering is to be expected during the installation. To ensure optimal installation, please allow Telus contractors to work without interruptions during this time.

Telus will NOT be installing suite devices at this point. A separate notice will be given to inform you of this procedure.

Parkade Sweep

Please be advised that the residential Parkade will be cleaned on the weekend of 7-9 DECEMBER.

In order to ensure the best possible results, all vehicles (including motorcycles) and items must be removed from the Parkade any time after 7PM on the 7th and before 8AM on the 8th. Nothing is to return until after 6PM on the 9th.

In order to accommodate resident parking, Impark has agreed to make the commercial parking levels available to residents at no charge. During the cleaning process, please feel free to park in the Impark area.

BUILDING WIDE WATER SHUTDOWN!

In order to conduct water supply investigations and repairs, the hot and cold water will be shut down intermittently on:

Sunday, 9 September from 10:00PM - 6:00AM

This shutdown will affect ALL units in ALL three towers and should not last beyond the time posted above.

Under NO circumstances may you or any contractor do any plumbing work during this time.

We understand that water shut downs are disruptive, but are occasionally necessary. Thank you for your understanding and consideration about this matter.

Parkade Wash & Sweep

Please be advised that the residential Parkade will be cleaned on the weekend of 22-24 JUNE.

In order to ensure the best possible results, all vehicles (including motorcycles) and items must be removed from the Parkade any time after 7PM on the 22nd and before 8AM on the 23rd. Nothing is to return until after 6PM on the 24th.

In order to accommodate resident parking, Impark has agreed to make the commercial parking levels available to residents at no charge. During the cleaning process, please feel free to park in the Impark area.

Elevator Fire Operation Testing

Elevator Fire Operation testing is slated to be conducted on Thursday, 7 June from 8:30-4:30pm.

During the testing, only one elevator per tower will be operational.

No move in/outs will be permitted during testing.

Power Shut Down

On FRIDAY, 20 April, from 2am until 10am, the power will be shut down on the main, second and parkade levels for critical electrical repairs.

The shut-down does not affect suite power. The parkade and residential hallways will be on emergency power. Overhead parkade doors will be operational.

One elevator in each tower will be operating during the shut-down.

Please direct any questions to the administration centre.

Elevator Fire Operation Testing

Elevator Fire Operation testing is slated to be conducted on Friday, 13 April from 8:30-4:30pm.

During the testing, only one elevator per tower will be operational.

No move in/outs will be permitted during testing.

Parkade Sweep

Please be advised that the residential Parkade will be cleaned on the weekend of 23-25 MARCH.

In order to ensure the best possible results, all vehicles and items must be removed from the Parkade any time after 7PM on the 23rd and before 8AM on the 24th. Nothing is to return until after 6PM on the 25th.

In order to accommodate resident parking, Impark has agreed to make the commercial parking levels available to residents at no charge. During the cleaning process, please feel free to park in the Impark area.

Annual Fire Alarm Testing

The Fire Bells in the common areas (Hallway, Parkade etc) will be ringing intermittently during the Annual Fire Inspection.

In addition, the ELEVATORS will have to be reset on occasion due to the alarm testing.

Testing will be conducted on WEDNESDAY, 10 January, and will ONLY occur between the hours of 8:30-4:30pm. Any alarms outside of these times should be considered regular fire alarms.

We do apologize for any interruption, but this is a requirement for the safety of all residents.

Thank you for your understanding and consideration about this matter.

Parkade Sweep

Please be advised that the residential Parkade will be cleaned on the weekend of 1-3 DECEMBER.

In order to ensure the best possible results, all vehicles and items must be removed from the Parkade any time after 7PM on the 1st and before 8AM on the 2nd. Nothing is to return until after 6PM on the 3rd.

In order to accommodate resident parking, Impark has agreed to make the commercial parking levels available to residents at no charge. During the cleaning process, please feel free to park in the Impark area.